Date: | 11 21 1912 |
---|---|
Description: | Elevated view within the coffer dam showing four steel draft tubes; wooden supports are visible inside one of the tubes. |
Date: | 11 21 1912 |
---|---|
Description: | Workmen posing on and in front of the steel draft tubes. The gate guides are visible on the right. |
Date: | 11 21 1912 |
---|---|
Description: | Elevated view of the progress of construction within the coffer dam showing the gate guides and draft tubes in place. Concrete forms and chutes, as well as... |
Date: | 11 21 1912 |
---|---|
Description: | Two workmen standing in the outlet of a steel draft tube in the power house, while other men are working above it. Cars are moving along the elevated trest... |
Date: | 12 29 1912 |
---|---|
Description: | Elevated view of the progress within the coffer dam showing concrete forms around the draft tubes and gate guides. The high trestle is seen extending to th... |
Date: | 02 08 1913 |
---|---|
Description: | A winter view with workers posing with brush mats at the power dam construction site. The gate guides and high trestle form the background. |
Date: | 03 11 1913 |
---|---|
Description: | Workers posing by a piling coated with sand suspended from a crane. |
Date: | 03 19 1913 |
---|---|
Description: | A view, looking east, of the wreckage of the high trestle caused by flooding and ice. The concrete plant is visible on the far bank. |
Date: | 04 07 1913 |
---|---|
Description: | Five men, two well-dressed, posing on electric rail cars during construction of the dam. |
Date: | 05 17 1913 |
---|---|
Description: | Progress on the power house construction, with the east portion of the wall complete, and men working on forms for the rest of the wall. |
Date: | 05 28 1913 |
---|---|
Description: | Completed east portion of the first story of the generator room of the power house. Forms are in place at the west end. |
Date: | 05 28 1913 |
---|---|
Description: | Workmen on temporary walkways among reinforcing bars on the roof of the power house. |
Date: | 06 13 1913 |
---|---|
Description: | Workmen and machinery at the quarry on Blackhawk Bluff. The gravel was used in construction of the power dam. |
Date: | 06 29 1913 |
---|---|
Description: | View from the west bank of the Wisconsin River showing progress on the power dam. The narrow gauge track is visible in the foreground. |
Date: | 07 18 1913 |
---|---|
Description: | Workers and a boy, Edgar Walch, posing on and around a steam shovel in the quarry at Eagle View Bluff. Edgar's father, Engelbert Walch, owned the steam sho... |
Date: | 07 29 1913 |
---|---|
Description: | A view of the power house from the southwest, showing bricklayers and other workers. The narrow gauge railroad is in the foreground. |
Date: | 09 01 1913 |
---|---|
Description: | Elevated view of the power house from the southwest showing progress of the brickwork. Two railroad cars are standing on the railroad extension. Workers ar... |
Date: | 10 10 1913 |
---|---|
Description: | Workers posing with roof trusses on the power house, 85 feet above the water level at the Prairie du Sac Dam. Note the brickwork in progress. |
Date: | 11 01 1913 |
---|---|
Description: | Elevated view from the hill, looking northeast at the power house at the Prairie du Sac dam. Much of the brickwork has been completed. Concrete forms for t... |
Date: | 02 01 1914 |
---|---|
Description: | A view looking west toward the lock and power house at the Prairie du Sac dam. Pilings and the elevated trestle are in the foreground. Men can be seen work... |