Date: | 03 19 1913 |
---|---|
Description: | A view, looking east, of the wreckage of the high trestle caused by flooding and ice. The concrete plant is visible on the far bank. |
Date: | 05 28 1913 |
---|---|
Description: | Completed east portion of the first story of the generator room of the power house. Forms are in place at the west end. |
Date: | 06 29 1913 |
---|---|
Description: | View from the west bank of the Wisconsin River showing progress on the power dam. The narrow gauge track is visible in the foreground. |
Date: | 09 01 1913 |
---|---|
Description: | Elevated view of the power house from the southwest showing progress of the brickwork. Two railroad cars are standing on the railroad extension. Workers ar... |
Date: | 10 10 1913 |
---|---|
Description: | Workers posing with roof trusses on the power house, 85 feet above the water level at the Prairie du Sac Dam. Note the brickwork in progress. |
Date: | 11 01 1913 |
---|---|
Description: | Elevated view from the hill, looking northeast at the power house at the Prairie du Sac dam. Much of the brickwork has been completed. Concrete forms for t... |
Date: | 03 11 1914 |
---|---|
Description: | Elevated view looking east from the lock at the Prairie du Sac dam. Recently completed buttresses are in the foreground, with earlier stages of constructio... |
Date: | 10 11 1914 |
---|---|
Description: | Elevated view looking east across the power house, lock, and uncompleted portion of the dam. The concrete plant is seen on the far bank. The rising water o... |
Date: | 02 28 1915 |
---|---|
Description: | Elevated view, looking east, of the power house, lock, and dam on the Wisconsin River. |
Date: | 1915 |
---|---|
Description: | Elevated view of a group of workers posing on the east bank of the Wisconsin River at the power dam construction site. One man is strumming his shovel like... |
Date: | 08 06 1911 |
---|---|
Description: | A view following the lower trestle to the west bank. The construction camp buildings, including the office and temporary power plant are seen on the left. |
Date: | 05 17 1912 |
---|---|
Description: | Elevated view of workers using shovels to level fresh concrete at the base of the chutes from the high trestle. The steam powered pile driver is at work in... |
Date: | 07 16 1912 |
---|---|
Description: | Workers posing inside the coffer dam. The narrow gauge railroad is behind them. One of the pile drivers is in the background. A bare area on the bluff in t... |
Date: | 08 01 1912 |
---|---|
Description: | Elevated view of the power dam construction site from the west, showing the elevated trestle, coffer dam, and steam pile drivers. The concrete plant is vis... |
Date: | 09 30 1912 |
---|---|
Description: | Forms have been removed from the first concrete poured for the power house in the northeast corner of the coffer dam. Men are pouring concrete from rail ca... |
Date: | 06 13 1913 |
---|---|
Description: | A view, from the west, of the quarry on Blackhawk Bluff. Gravel from the quarry was used in concrete for the construction of the power plant and dam. |
Date: | 07 02 1913 |
---|---|
Description: | Workers pause while installing a maze of conduit for the switchboard in the power house. The construction camp is to the left. |
Date: | 1910 |
---|---|
Description: | Elevated view of high water on the Wisconsin River from a bluff on the west bank. The photograph is undated and does not indicate if it was taken prior to ... |
Date: | 1907 |
---|---|
Description: | A view of the west bank of the Wisconsin River at Pounds Landing. This bluff is at the western end of the power dam which was constructed 1911-1914. Captio... |
Date: | 05 28 1911 |
---|---|
Description: | Men posing on a barge carrying a steam powered pile driver at work on the coffer dam for the construction of the powerhouse. Caption reads: "Driving Sheet ... |