Date: | 10 07 1911 |
---|---|
Description: | Elevated view of the rising waters of the Wisconsin River at the construction site. This view shows the coffer dam, pile drivers, and narrow gauge railroad... |
Date: | 10 07 1911 |
---|---|
Description: | Workers attempt to secure the trestle against high water on the Wisconsin River during construction of the power dam. |
Date: | 10 11 1911 |
---|---|
Description: | Elevated view of high water on the Wisconsin River which has inundated the coffer dam at the construction site. The narrow gauge railroad (curved line in f... |
Date: | 10 12 1911 |
---|---|
Description: | High water on the Wisconsin River has submerged the coffer dam and trestle. Two pile drivers remain in place. Log pilings are floating near the western sh... |
Date: | 10 12 1911 |
---|---|
Description: | Two men are standing on the tracks of the newly constructed railroad extension to the construction site of the Prairie du Sac dam. Behind them, the tracks... |
Date: | 10 18 1911 |
---|---|
Description: | Receding flood waters reveal destruction of the railroad extension to the power dam construction site. |
Date: | 10 18 1911 |
---|---|
Description: | Workmen standing on damaged and partly submerged railroad track on the west shore of the Wisconsin River. |
Date: | 11 05 1911 |
---|---|
Description: | A diver and team working to inspect the coffer dam for underwater damage caused by flooding. |
Date: | 05 03 1912 |
---|---|
Description: | Workmen on a barge using a pulley to raise sheet steel pilings which were damaged by high water in October, 1911. |
Date: | 03 19 1913 |
---|---|
Description: | A view, looking east, of the wreckage of the high trestle caused by flooding and ice. The concrete plant is visible on the far bank. |
Date: | 10 12 1911 |
---|---|
Description: | High water has scattered timber pilings through the construction camp. The office is on the right; the smokestacks of the temporary power plant are behind ... |
Date: | 08 01 1912 |
---|---|
Description: | Elevated view of the power dam construction site from the west, showing the elevated trestle, coffer dam, and steam pile drivers. The concrete plant is vis... |