Date: | 06 19 1911 |
---|---|
Description: | Looking west over the Wisconsin River at the unfinished narrow gauge railroad trestle built for construction of the dam. Two pile drivers are seen in the a... |
Date: | 06 21 1911 |
---|---|
Description: | Looking east over the Wisconsin River showing the unfinished narrow gauge railroad trestle. Two steam-driven pile drivers on barges with construction worke... |
Date: | 07 01 1911 |
---|---|
Description: | A steam-powered centrifugal sand pump at work on the Wisconsin River during the construction of the power dam. Pilings of the coffer dam are visible in the... |
Date: | 08 15 1911 |
---|---|
Description: | Dam site on the Wisconsin river, looking southwest along the unfinished narrow gauge railroad trestle. The coffer dam and two pile drivers are also visible... |
Date: | 09 12 1911 |
---|---|
Description: | An overview of the dam site on the Wisconsin River from the west shore. Three pile drivers are at work on the coffer dam. The railroad trestle is in the ... |
Date: | 09 18 1911 |
---|---|
Description: | Elevated view of pile drivers at work on the coffer dam. Pilings are also floating within the confines of the dam. The shoreline can be seen in the backgro... |
Date: | 10 07 1911 |
---|---|
Description: | Workers attempt to secure the trestle against high water on the Wisconsin River during construction of the power dam. |
Date: | 10 07 1911 |
---|---|
Description: | Two men in a boat approaching a wooden gravel bin at the construction site. Other men are watching from atop the structure and from the shore. |
Date: | 10 12 1911 |
---|---|
Description: | Two men are standing on the tracks of the newly constructed railroad extension to the construction site of the Prairie du Sac dam. Behind them, the tracks... |
Date: | 10 18 1911 |
---|---|
Description: | Workmen standing on damaged and partly submerged railroad track on the west shore of the Wisconsin River. |
Date: | 01 20 1912 |
---|---|
Description: | Elevated view of two men standing on a rail car on the narrow gauge electric railroad crossing the river at the dam construction site. The portion of track... |
Date: | 05 03 1912 |
---|---|
Description: | Workmen on a barge using a pulley to raise sheet steel pilings which were damaged by high water in October, 1911. |
Date: | 05 17 1912 |
---|---|
Description: | Workmen pouring concrete from the elevated railroad into forms below. |
Date: | 05 31 1912 |
---|---|
Description: | Workmen posing outside the dining hall before dinner. |
Date: | 06 16 1912 |
---|---|
Description: | Elevated view of steam powered pile drivers at work on the coffer dam. |
Date: | 07 16 1912 |
---|---|
Description: | An overview, from the west bank, of the power dam construction site. The high trestle is in the background, and the narrow gauge electric railroad is in th... |
Date: | 10 17 1912 |
---|---|
Description: | Concrete plant at east end of the dam, showing the mixers, crane, and a rail car at the abutment. |
Date: | 11 02 1912 |
---|---|
Description: | Workmen using a crane to erect the gate guides for the power house. |
Date: | 11 02 1912 |
---|---|
Description: | Workmen posing during erection of the draft tubes for the power house at the Prairie du Sac dam. |
Date: | 11 21 1912 |
---|---|
Description: | Elevated view within the coffer dam showing four steel draft tubes; wooden supports are visible inside one of the tubes. |